Shift to Oil-Fired Power Plants Hinges on ৳10,000 Crore Debt Clearance

A high-voltage electric power grid line operating in Bangladesh during the energy crisis.
Md. Tareq; Dbarta24 –  The Bangladesh Power Development Board (PDB) is seeking to ramp up electricity generation from furnace oil-based power plants to mitigate the severe ongoing natural gas shortage.
 
However, independent power producers (IPPs) have cautioned that expanding production is unfeasible without resolving an outstanding bill crisis amounting to nearly ৳10,000 crore (approximately $820 million).

Gas Shortages Force Emergency Shift

Depleting domestic natural gas reserves alongside frequent disruptions in liquefied natural gas (LNG) imports have left gas-based power generation operating well below capacity.
 
To cushion key industries, authorities decided to divert available natural gas supplies to industrial sectors, effectively forcing the PDB to lean heavily on liquid fuels for grid stability.

According to PDB data, grid-based power generation capacity stands at 29,593 MW.
 
Gas-based plants account for the largest share at 12,472 MW (42%), while furnace oil-based facilities represent 5,641 MW (19%). Coal covers 7,203 MW, renewables contribute 1,129 MW, diesel accounts for 768 MW, and electricity imports make up the remaining 2,696 MW.

Financial Bottlenecks Threaten Supply

The Bangladesh Independent Power Producers Association (BIPPA) confirmed that while PDB has requested roughly 4,000 MW of oil-fired electricity, private plants are currently producing around 2,600 MW.

BIPPA President David Hasnat indicated that private producers could readily supply an additional 2,500 MW if financial constraints are resolved.
 
Hasnat explained that while expecting a full payout at once might be realistic, clearing dues up to at least the last two months would enable plant owners to open fresh Letters of Credit (LCs) to import fuel.

Former BIPPA President Imran Karim added that beyond unpaid electricity bills, issues surrounding liquidated damages (LD) and penalties imposed by PDB must also be addressed.
 
He emphasized that while private plants remain grid-ready, securing immediate fuel financing is a prerequisite.

Short-Term Fix vs. Long-Term Fiscal Strain

Energy experts warn that while turning back to furnace oil offers quick relief, it comes at a steep financial cost.

“In the current crisis, the government must balance keeping the power grid stable while keeping industries running,” said energy expert Professor M. Tamim. “Relying on oil-fired plants may work as an immediate emergency measure, but operating them long-term will escalate PDB’s financial burden. It is a temporary workaround, not a permanent solution.”
Sector insiders emphasize that while liquid fuels can plug immediate capacity gaps, the strategy exposes the government to elevated fuel import expenses and deeper structural debt.
 
Experts urge the government to expedite domestic gas exploration and production alongside stabilizing LNG imports to establish long-term energy security.